Production capacity for 100 units per year, with additional capacity coming online in 2027. Current lead time for FP-MPT standard configurations is 12–14 months; engineered-to-order units are quoted per project. The delivery date, inclusive of engineering, test, and transport, is committed in the order.
| Stage | What happens |
|---|---|
| Order | Purchase order; production slot reserved, delivery date committed |
| Engineering | Drawings for approval; long-lead materials committed. Monthly order status reports from here to delivery: engineering, materials, production, test, transit |
| Production | Core, windings, assembly, vacuum drying, oil processing |
| FAT | Full routine test program, witnessed; test report issued |
| Transport | Packing with impact recorders; transport to your site |
| Site | Offloading, assembly, vacuum oil filling, site tests, and commissioning |
Every unit ships with a Farpoint warranty of 36 months from energization, with the unit stored to Farpoint's storage procedure before energization, covering materials, workmanship, and design. Repair or replacement is at Farpoint's cost, including transport and site labor. The warranty is assignable to your lender or a successor owner. Coverage extends to five years from energization as an option.