Quality

Engineered, inspected, and tested for the duty

Engineering

Engineering review covers short-circuit withstand, thermal duty and insulation coordination against the applicable IEEE C57 or project requirements. Design calculations, including finite-element analysis where required, support the proposed design. Drawings, nameplate and test plan are issued for the specified buyer and utility approvals before the relevant production stages.

Inspection

A stage-gated inspection and test plan with hold, witness and review points is issued for your sign-off before production. For liquid-filled power units, stages include core build, winding, assembly, drying and oil processing. Core steel, conductor and insulation traceability is included in the plan. Your inspector is welcome at the agreed hold and witness points.

Testing

Factory tests verify the ordered transformer against its specification and applicable standard. The test plan defines the required electrical, dielectric and functional checks, supporting design tests, and any additional measurements. Buyer witness points are scheduled with your engineer at order.

Documentation

Test reports, final drawings and the operating and maintenance manual form the digital dossier, kept by serial number. Oil certificates, frequency-response and dissolved-gas baselines, impact-recorder logs and commissioning reports are included where applicable to the equipment and supplied scope.

For your engineering team

Test program, inspection points, standards, and interfaces

Factory test program — project scope and IEEE C57.12.90

The detailed program below covers tests and records considered for power-transformer orders. Distribution transformers use the tests applicable to their design and specified standard. The agreed plan identifies required measurements, design evidence and additional tests for each package.

TestScope
Factory measurements and checks — scope set for the equipment
Winding resistanceSpecified windings and tap positions
Ratio, polarity, and phase relationSpecified tap positions and connections
No-load loss and excitation currentAt rated voltage; 110 % excitation where required
Load loss and impedanceAt rated current and specified taps and cooling-stage ratings
Zero-sequence impedanceWhere specified for grounded-wye systems and relay settings
Applied-voltage testLow-frequency dielectric; test levels for the specified insulation class
Induced-voltage test with partial dischargePartial-discharge measurement, enhancement and one-hour levels where required by the selected test procedure
Lightning impulseFull and chopped wave where required, at the specified terminals and test levels
Insulation power factor and resistanceWindings and bushings; C1 / C2 measurements where applicable
Core ground insulationCore-to-ground and core-to-frame
Leak and pressure testLiquid-filled tanks and radiators, as applicable
Sweep-frequency response baselineWhen specified: reference fingerprint before shipment, compared at site
Oil testsFor liquid-filled equipment: specified dielectric strength, moisture, power factor, corrosive sulfur, furans and DGA tests; pre- and post-dielectric samples where required
Current transformersWhere fitted: ratio, polarity and excitation
Functional checksCooling, controls, alarms, and LTC operation where fitted
Design tests — applicable reports or project testing
Temperature riseSpecified cooling stages; repeated on individual units when required
Audible soundApplicable sound standard and project limits; NEMA TR-1 where specified; unit repeat tests when required
Lifting, jacking, and transport fixturesMechanical verification
Other — when specified
Short-circuit withstand verificationTest or calculation and similar-design evidence to the agreed specification; IEEE C57.12.90 and finite-element force analysis where applicable
Radio-influence voltageCorona check on bushings and terminals
Extended temperature-rise or sound programPer your specification
Inspection and test plan

The stages below illustrate a liquid-filled power-transformer inspection plan. Equipment-specific plans identify the applicable stages and mark each point hold, witness or review.

  • Material receipt: core steel, conductor and insulation traceability
  • Core stacking complete
  • Winding completion, each winding
  • Core-and-coil assembly, before drying
  • Vacuum drying end point: moisture and dew point
  • Tanking and oil filling under vacuum
  • Final assembly and pre-test checks
  • Factory acceptance test — agreed buyer witness points
  • Packing, specified transport monitoring and release for shipment
Site program

Site services and measurements are selected for the equipment, transport condition and agreed commissioning scope.

  • Receiving inspection and any impact-recorder review
  • For gas-shipped units: dew-point and oxygen check before oil filling
  • SFRA compared with the factory baseline where specified
  • Pre-energization tests for the equipment; IEEE C57.152 where applicable
  • DGA at energization and after the first month of service when included in the site program
Standards

The applicable standards, editions and technical exceptions are identified in the quotation. The references below are selected according to product, voltage class, duty and supplied accessories.

IEEE C57.12.00 · C57.12.10 · C57.12.90 · C57.91 · C57.110 · C57.159 · C57.104 · C57.149 · C57.152 · C57.106 · C57.147 · C57.19.00 · C57.13 · C57.131 · C57.93 · IEEE 693 · NEMA TR-1 · ASTM D3487

Built to IEC 60076 or regional specifications when the project requires it.

Interfaces and submittals

Power-transformer interface examples: multi-ratio bushing current transformers, relay accuracy class C800 where specified, neutral CT on grounded-wye windings · control power 125 V DC and 120/240 V AC, 480 V for cooling where required · alarm and trip contacts for temperature, pressure, liquid level and gas · DNP3 or IEC 61850 monitoring options · approval package: outline, nameplate, control schematics, CT curves and bushing drawings as applicable. Distribution-package interfaces are set by the installation and equipment specification.

Bring your inspector

Your engineer or third-party inspector is welcome at the agreed hold points and factory acceptance test. We schedule it with you at order.

Request a quotation